Upgrading of Kenyalang Interchange & Jalan Lapangan Terbang, and Proposed New KIA / Jalan Stutong Link Road, Kuching, Sarawak
Prior to the upgrading works, the BDC Roundabout was heavily congested for all the five legs including the route to and from the Kuching International Airport. Upgrading was therefore necessary to ensure that the protocol road provides uninterrupted journey to and from the Kuching International Airport besides bringing relief to regular road users in the area.
The Interchange upgrading adopted a design concept for the superstructure that is slim and open to provide pleasing aesthetics and minimum visual obstruction for motorists. A design speed of 70km/hr has been adopted except for the semi directional ramps where the speed is 40km.hr.
The superstructure consists of five flyover bridges ranging from 247m to 461m long giving a total of 1835m. Each bridge carries two 3.5m traffic lanes with marginal strips on both sides of the carriageway. The interchange upgrading also include re-alignment of the at grade slip roads, construction of motorcycle lanes and foot paths and relocation of affected utilities.
Project on going
Project 1: Upgrading of Kenyalang Interchange
| Client |
: |
Government of Malaysia (Ministry of Public Work) |
| Contract Value |
: |
RM 71,000,000.00 |
| Date of Award |
: |
12th December 2006 |
| Date of Completion |
: |
11th June 2008 |
| Project description |
: |
Upgrade Kenyalang Interchange
|
Project scope of works involves the following:
Project 2: Kuching International Airport (KIA) / Stutong Link Road
| Client |
: |
Government of Malaysia (Ministry of Public Work) |
| Contract Value |
: |
RM 19,300,000.00 |
| Date of Award |
: |
12th December 2006 |
| Date of Completion |
: |
11th December 2008 |
| Project description |
: |
Construct a new road linking the Kuching International Airport to the Kenyalang Interchange.
|
Project scope of works involves the following:
|